Hinkson Creek Stabilization (Update)

Share Hinkson Creek Stabilization (Update) on Facebook Share Hinkson Creek Stabilization (Update) on Twitter Share Hinkson Creek Stabilization (Update) on Linkedin Email Hinkson Creek Stabilization (Update) link

Construction on the Hinkson Creek stabilization project is nearly complete. Thank to everyone who provided feedback on this project.

Update, July 22: Construction on the Hinkson Creek stabilization project is nearly complete. Photos of the linear peak stone toe are in the column on the right.


The City of Columbia Sewer and Stormwater Utilities are working to stabilize the Hinkson Creek streambank. The project has three main goals: to protect sewer lines from damage, to reduce sediment from entering the creek, and to enhance habitat for macroinvertebrates. All three will lead to improved water quality in Hinkson Creek.

A contractor of the Utilities worked on the project July 11-22. The improvements included installing 430 feet of linear peak stone toe and five bendway weirs.

Linear peak stone toe stabilization is the strategic placement of large rocks and downed trees into the channel to divert stream flow away from the existing bank. In the Hinkson, the plan is to construct the top of the linear peak stone toe 1 to 2 feet above ordinary high-water elevation. The toe will support the weight of the bank, over time creating a stable slope behind the row of stones through the deposit of sediments and the slumping of the upper bank.

Along with downed trees and root balls, the Utility plans to install native plants to help secure the bank. These materials will enhance habitat for stream life.

All necessary Army Corps of Engineers and Missouri Department of Natural Resources permits have been obtained. The Hinkson Creek Collaborative Adaptive Management teams also approved this project. The cost for this project is estimated at $220,000 from Sewer Utility and Storm Water Utility funds.

Update, July 22: Construction on the Hinkson Creek stabilization project is nearly complete. Photos of the linear peak stone toe are in the column on the right.


The City of Columbia Sewer and Stormwater Utilities are working to stabilize the Hinkson Creek streambank. The project has three main goals: to protect sewer lines from damage, to reduce sediment from entering the creek, and to enhance habitat for macroinvertebrates. All three will lead to improved water quality in Hinkson Creek.

A contractor of the Utilities worked on the project July 11-22. The improvements included installing 430 feet of linear peak stone toe and five bendway weirs.

Linear peak stone toe stabilization is the strategic placement of large rocks and downed trees into the channel to divert stream flow away from the existing bank. In the Hinkson, the plan is to construct the top of the linear peak stone toe 1 to 2 feet above ordinary high-water elevation. The toe will support the weight of the bank, over time creating a stable slope behind the row of stones through the deposit of sediments and the slumping of the upper bank.

Along with downed trees and root balls, the Utility plans to install native plants to help secure the bank. These materials will enhance habitat for stream life.

All necessary Army Corps of Engineers and Missouri Department of Natural Resources permits have been obtained. The Hinkson Creek Collaborative Adaptive Management teams also approved this project. The cost for this project is estimated at $220,000 from Sewer Utility and Storm Water Utility funds.

Construction on the Hinkson Creek stabilization project is nearly complete. Thank to everyone who provided feedback on this project.

Ask any questions about the Hinkson Creek Stabilization project here, and a City Staff member will get back to you as soon as possible.

  • Share I’d like to help on Facebook Share I’d like to help on Twitter Share I’d like to help on Linkedin Email I’d like to help link

    I’d like to help

    Michael asked over 2 years ago

    Michael, thank you for your interest in this project. For safety reasons, we cannot allow public involvement at this time. We have hired a contractor to construct the stone toe and the bendway weirs. The presence of heavy machinery, heavy rocks, steep slopes and water means we have to make safety our No. 1 priority. Only Utilities staff and construction crews will be allowed during construction.

    However, there might be opportunities to volunteer after the construction has been completed.