A crane lifts a piece of the cA crane lifts a piece of the clarifier out of Basin 3. The concrete will be repaired before baffle curtains will be installed.
A worker pressure washes some A worker pressure washes some of the coating off the wall in Secondary Basin 3.
A worker pressure washes some of the coating off the wall in Secondary Basin 3.
A jackhammer on the crane knocA jackhammer on the crane knocks down the walls of a lime silo.
A jackhammer on the crane knocks down the walls of a lime silo.
Workers pour concrete into theWorkers pour concrete into the framing at the center of Basin 3. The ground beneath the floor of the basin was repaired, which will improve operations.
Workers pour concrete into the framing at the center of Basin 3. The ground beneath the floor of the basin was repaired, which will improve operations.
Crews maneuver the core of theCrews maneuver the core of the clarifier into place in Primary Basin 3.
Crews maneuver the core of the clarifier into place in Primary Basin 3.
A crane moves a piece of the rA crane moves a piece of the roof into position at the Chemical Building.
Crews align the motor on top oCrews align the motor on top of the propeller in Basin 3.
A crane carries the bridge thaA crane carries the bridge that spans Basin 3 over the aerators and into place.
Crews guide the rake arm into Crews guide the rake arm into place in the bottom of Primary Basin 3.
A bubble test ensured the reliA bubble test ensured the reliability of Filters 1 and 2.
Crews did a bubble test to ensure the filters’ reliability. To do the bubble test, crews partially filled the filter housing with water then pumped air upward through the filter at increasing pressure until bubbles could be seen.