McBaine Water Treatment Plant improvement project
The City of Columbia is working to improve the McBaine Water Treatment Plant. The project is expected to restore the plant’s capacity to treat 32 million gallons of water per day and includes rehabilitation and replacement projects that will enhance the performance of and extend the life of the facility.
To learn more about this project, visit the project page on the City's website.
Want to know more about the City of Columbia's water treatment process? Click here.
Oct. 31, 2024
Rehabilitation on Primary and Secondary Basin 3 has continued over the past couple of weeks. Crews used a jackhammer to break away the concrete in the middle of Primary Basin 3. Some excess groundwater got under the basin and caused the floor to become uneven. Appropriate drainage will be installed before the concrete is poured. Crews also began removing a coating off the concrete inside the basins -- some by scraping, some by jackhammering and some by pressure washing. After the coating has been removed, crews will repair flaws in the concrete with an injection method.
Click for photo | Click for photo | Click for video |
---|---|---|
Meanwhile, over at the Chemical Building, piping for water and the different chemicals has been installed in the ground. Electric conduits were scheduled to be installed before the concrete floor could be poured. The chemical that the pipes will be used for is indicated by the color of the tape rings. The number of tape rings is a guide so crews know which pipe is which.
Click for photo | Click for photo | |
---|---|---|
An old lime silo and the crane structure have been removed. The lime silo had not been used since the 2005 expansion, when a new silo had been erected.
Click for photo | Click for video | Click for photo |
---|---|---|
Oct. 1, 2024
The walkways, weirs and clarifier have been removed from Basin 3. The clarifier keeps influent water moving while suspended solids clump together and settle to the bottom of the basin and removed. The water at the top flows into weirs, which direct the water for secondary clarifying. Construction crews have begun making preparations to pour new concrete in the basin before the installation of new equipment. Crews have also started work removing the equipment from the secondary clarifier No. 3. In the secondary basin, crews will install baffle curtains, which will help the Utility improve treatment efficiency.
Click for photo | Click for photo | Click for photo |
---|---|---|
Click for video | Click for photo | Click for photo |
---|---|---|
Aerator 3 has been removed. Crews have it timed so that at least two of the four aerators will remain in service during the winter months.
With the new aerators, staff will be able to back a truck to the aerators for media cartridge removal and maintenance.
Click for photo | Click for photo | |
---|---|---|
The pile testing has been completed, and construction of the new chemical building will begin.
Sept. 10, 2024
Preparations are underway as the McBaine Water Treatment Plant Improvement Project begins.
Crews began pile load testing this week before construction of the new Chemical Feed Building. Piles are concrete cylinders driven into the ground at the proposed construction site. Testing piles by applying force will allow Bowen Construction to gather information about the soil and optimize design for the proposed building. Bowen Construction will be testing 36 piles to collect the data.
Click for photo | Click for photo | Click for photo |
---|---|---|
Primary and Secondary Basin 3 were emptied prior to construction. Demolition of the Lime Silo and Aerator No. 3 was scheduled to begin this week.
Click for photo | ||
---|---|---|
Water Treatment Plant comments and QandA
Please leave your comments or questions about the McBaine Water Treatment Plant Improvement Project. City staff will respond to your inquiry as soon as possible.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends