McBaine Water Treatment Plant improvement project

Share McBaine Water Treatment Plant improvement project on Facebook Share McBaine Water Treatment Plant improvement project on Twitter Share McBaine Water Treatment Plant improvement project on Linkedin Email McBaine Water Treatment Plant improvement project link

The City of Columbia is working to improve the McBaine Water Treatment Plant. The project is expected to restore the plant’s capacity to treat 32 million gallons of water per day and includes rehabilitation and replacement projects that will enhance the performance of and extend the life of the facility.

To learn more about this project, visit the project page on the City's website.

Want to know more about the City of Columbia's water treatment process? Click here.


Oct. 31, 2024

Rehabilitation on Primary and Secondary Basin 3 has continued over the past couple of weeks. Crews used a jackhammer to break away the concrete in the middle of Primary Basin 3. Some excess groundwater got under the basin and caused the floor to become uneven. Appropriate drainage will be installed before the concrete is poured. Crews also began removing a coating off the concrete inside the basins -- some by scraping, some by jackhammering and some by pressure washing. After the coating has been removed, crews will repair flaws in the concrete with an injection method.

Click for photoClick for photoClick for video
The center of Primary Basin 3 is being removed and a new floor will be poured. In the background, another worker has begun stripping the coating off the concrete.A worker pressure washes some of the coating off the wall in Secondary Basin 3.


Meanwhile, over at the Chemical Building, piping for water and the different chemicals has been installed in the ground. Electric conduits were scheduled to be installed before the concrete floor could be poured. The chemical that the pipes will be used for is indicated by the color of the tape rings. The number of tape rings is a guide so crews know which pipe is which.

Click for photoClick for photo
Chemical pipes are laid in the trench before concrete is poured. Once electrical conduits are installed, crews will begin construction of the Chemical Building.Connectors for the chemicals have been installed at the site of the Chemical Building. The pipes are coordinated by the number of tape stripes on the outside.


An old lime silo and the crane structure have been removed. The lime silo had not been used since the 2005 expansion, when a new silo had been erected.

Click for photoClick for videoClick for photo
A jackhammer on the crane knocks down the walls of a lime silo.

A jackhammer on the crane knocks down the walls of a lime silo.

Oct. 1, 2024

The walkways, weirs and clarifier have been removed from Basin 3. The clarifier keeps influent water moving while suspended solids clump together and settle to the bottom of the basin and removed. The water at the top flows into weirs, which direct the water for secondary clarifying. Construction crews have begun making preparations to pour new concrete in the basin before the installation of new equipment. Crews have also started work removing the equipment from the secondary clarifier No. 3. In the secondary basin, crews will install baffle curtains, which will help the Utility improve treatment efficiency.

Click for photoClick for photoClick for photo
This image illustrates what a full basin looks like.Workers dismantles the clarifier to prepare it for removal from Basin 3.
A construction worker disassembles the clarifier in Basin 3.


Click for videoClick for photoClick for photo
A crane lifts a piece of the clarifier out of Basin 3. The concrete will be repaired before new equipment is installed.
A crane lifts part of the clarifier mechanism out of Basin 3.


Basin 3 without the clarifier. Crews will have to remove the center part of the floor to ensure it is level before removing the coating and making concrete repairs.


Aerator 3 has been removed. Crews have it timed so that at least two of the four aerators will remain in service during the winter months.

With the new aerators, staff will be able to back a truck to the aerators for media cartridge removal and maintenance.

Click for photoClick for photo
A worker prepares Aerator 3 for disassembly.A worker detaches a pipe so Aerator 3 can be removed.


The pile testing has been completed, and construction of the new chemical building will begin.

Sept. 10, 2024

Preparations are underway as the McBaine Water Treatment Plant Improvement Project begins.

Crews began pile load testing this week before construction of the new Chemical Feed Building. Piles are concrete cylinders driven into the ground at the proposed construction site. Testing piles by applying force will allow Bowen Construction to gather information about the soil and optimize design for the proposed building. Bowen Construction will be testing 36 piles to collect the data.

Click for photoClick for photoClick for photo
Construction crews look over pile load testing.A drill is used to conduct pile testing.Hardened concrete shows how the ground will react to a building.


Primary and Secondary Basin 3 were emptied prior to construction. Demolition of the Lime Silo and Aerator No. 3 was scheduled to begin this week.

Click for photo

Basin 3 was emptied prior to the beginning of the Water Treatment Plant Improvement Project. The equipment was scheduled to be removed and the basin rehabilitated before new equipment could be installed

The City of Columbia is working to improve the McBaine Water Treatment Plant. The project is expected to restore the plant’s capacity to treat 32 million gallons of water per day and includes rehabilitation and replacement projects that will enhance the performance of and extend the life of the facility.

To learn more about this project, visit the project page on the City's website.

Want to know more about the City of Columbia's water treatment process? Click here.


Oct. 31, 2024

Rehabilitation on Primary and Secondary Basin 3 has continued over the past couple of weeks. Crews used a jackhammer to break away the concrete in the middle of Primary Basin 3. Some excess groundwater got under the basin and caused the floor to become uneven. Appropriate drainage will be installed before the concrete is poured. Crews also began removing a coating off the concrete inside the basins -- some by scraping, some by jackhammering and some by pressure washing. After the coating has been removed, crews will repair flaws in the concrete with an injection method.

Click for photoClick for photoClick for video
The center of Primary Basin 3 is being removed and a new floor will be poured. In the background, another worker has begun stripping the coating off the concrete.A worker pressure washes some of the coating off the wall in Secondary Basin 3.


Meanwhile, over at the Chemical Building, piping for water and the different chemicals has been installed in the ground. Electric conduits were scheduled to be installed before the concrete floor could be poured. The chemical that the pipes will be used for is indicated by the color of the tape rings. The number of tape rings is a guide so crews know which pipe is which.

Click for photoClick for photo
Chemical pipes are laid in the trench before concrete is poured. Once electrical conduits are installed, crews will begin construction of the Chemical Building.Connectors for the chemicals have been installed at the site of the Chemical Building. The pipes are coordinated by the number of tape stripes on the outside.


An old lime silo and the crane structure have been removed. The lime silo had not been used since the 2005 expansion, when a new silo had been erected.

Click for photoClick for videoClick for photo
A jackhammer on the crane knocks down the walls of a lime silo.

A jackhammer on the crane knocks down the walls of a lime silo.

Oct. 1, 2024

The walkways, weirs and clarifier have been removed from Basin 3. The clarifier keeps influent water moving while suspended solids clump together and settle to the bottom of the basin and removed. The water at the top flows into weirs, which direct the water for secondary clarifying. Construction crews have begun making preparations to pour new concrete in the basin before the installation of new equipment. Crews have also started work removing the equipment from the secondary clarifier No. 3. In the secondary basin, crews will install baffle curtains, which will help the Utility improve treatment efficiency.

Click for photoClick for photoClick for photo
This image illustrates what a full basin looks like.Workers dismantles the clarifier to prepare it for removal from Basin 3.
A construction worker disassembles the clarifier in Basin 3.


Click for videoClick for photoClick for photo
A crane lifts a piece of the clarifier out of Basin 3. The concrete will be repaired before new equipment is installed.
A crane lifts part of the clarifier mechanism out of Basin 3.


Basin 3 without the clarifier. Crews will have to remove the center part of the floor to ensure it is level before removing the coating and making concrete repairs.


Aerator 3 has been removed. Crews have it timed so that at least two of the four aerators will remain in service during the winter months.

With the new aerators, staff will be able to back a truck to the aerators for media cartridge removal and maintenance.

Click for photoClick for photo
A worker prepares Aerator 3 for disassembly.A worker detaches a pipe so Aerator 3 can be removed.


The pile testing has been completed, and construction of the new chemical building will begin.

Sept. 10, 2024

Preparations are underway as the McBaine Water Treatment Plant Improvement Project begins.

Crews began pile load testing this week before construction of the new Chemical Feed Building. Piles are concrete cylinders driven into the ground at the proposed construction site. Testing piles by applying force will allow Bowen Construction to gather information about the soil and optimize design for the proposed building. Bowen Construction will be testing 36 piles to collect the data.

Click for photoClick for photoClick for photo
Construction crews look over pile load testing.A drill is used to conduct pile testing.Hardened concrete shows how the ground will react to a building.


Primary and Secondary Basin 3 were emptied prior to construction. Demolition of the Lime Silo and Aerator No. 3 was scheduled to begin this week.

Click for photo

Basin 3 was emptied prior to the beginning of the Water Treatment Plant Improvement Project. The equipment was scheduled to be removed and the basin rehabilitated before new equipment could be installed

Water Treatment Plant comments and QandA

Please leave your comments or questions about the McBaine Water Treatment Plant Improvement Project. City staff will respond to your inquiry as soon as possible.

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share How do these city bonds work? Is this an investment opportunity and if so what is the interest? on Facebook Share How do these city bonds work? Is this an investment opportunity and if so what is the interest? on Twitter Share How do these city bonds work? Is this an investment opportunity and if so what is the interest? on Linkedin Email How do these city bonds work? Is this an investment opportunity and if so what is the interest? link

    How do these city bonds work? Is this an investment opportunity and if so what is the interest?

    RogerWink asked about 1 year ago

    The auction sale and results will be posted to http://www.columbiacapitalauction.com.

  • Share Does the project include addressing security issues to the wells and pumps to prevent unauthorized access to critical infrastructure? on Facebook Share Does the project include addressing security issues to the wells and pumps to prevent unauthorized access to critical infrastructure? on Twitter Share Does the project include addressing security issues to the wells and pumps to prevent unauthorized access to critical infrastructure? on Linkedin Email Does the project include addressing security issues to the wells and pumps to prevent unauthorized access to critical infrastructure? link

    Does the project include addressing security issues to the wells and pumps to prevent unauthorized access to critical infrastructure?

    Steven Sapp asked about 1 year ago

    That is currently being addressed 

  • Share Where will the bonds be offered for sale? on Facebook Share Where will the bonds be offered for sale? on Twitter Share Where will the bonds be offered for sale? on Linkedin Email Where will the bonds be offered for sale? link

    Where will the bonds be offered for sale?

    Dannynuhi asked about 1 year ago

    The auction sale and results will be posted to http://www.columbiacapitalauction.com.

  • Share We need to provide the upgrades needed to this plan to ensure that our water system is up to date and the water quality meets the standards outlined by the COMO Safe Water Coalition. Our current system is not meeting those standards. on Facebook Share We need to provide the upgrades needed to this plan to ensure that our water system is up to date and the water quality meets the standards outlined by the COMO Safe Water Coalition. Our current system is not meeting those standards. on Twitter Share We need to provide the upgrades needed to this plan to ensure that our water system is up to date and the water quality meets the standards outlined by the COMO Safe Water Coalition. Our current system is not meeting those standards. on Linkedin Email We need to provide the upgrades needed to this plan to ensure that our water system is up to date and the water quality meets the standards outlined by the COMO Safe Water Coalition. Our current system is not meeting those standards. link

    We need to provide the upgrades needed to this plan to ensure that our water system is up to date and the water quality meets the standards outlined by the COMO Safe Water Coalition. Our current system is not meeting those standards.

    Srenee.carter58 asked about 2 years ago

     Thank you for your input.

  • Share So this is a side observation to this project since it is already on the table... Columbia should be looking ahead and this is one of those projects that could really shoot this community forward = someone please check out this video from youtube to see what I mean!!! It's about turning waste into energy!!! Seriously, it's a game changer and could make a huge change in pollution AND the cost of utilities in the area! https://youtu.be/p6CF-umWLZg on Facebook Share So this is a side observation to this project since it is already on the table... Columbia should be looking ahead and this is one of those projects that could really shoot this community forward = someone please check out this video from youtube to see what I mean!!! It's about turning waste into energy!!! Seriously, it's a game changer and could make a huge change in pollution AND the cost of utilities in the area! https://youtu.be/p6CF-umWLZg on Twitter Share So this is a side observation to this project since it is already on the table... Columbia should be looking ahead and this is one of those projects that could really shoot this community forward = someone please check out this video from youtube to see what I mean!!! It's about turning waste into energy!!! Seriously, it's a game changer and could make a huge change in pollution AND the cost of utilities in the area! https://youtu.be/p6CF-umWLZg on Linkedin Email So this is a side observation to this project since it is already on the table... Columbia should be looking ahead and this is one of those projects that could really shoot this community forward = someone please check out this video from youtube to see what I mean!!! It's about turning waste into energy!!! Seriously, it's a game changer and could make a huge change in pollution AND the cost of utilities in the area! https://youtu.be/p6CF-umWLZg link

    So this is a side observation to this project since it is already on the table... Columbia should be looking ahead and this is one of those projects that could really shoot this community forward = someone please check out this video from youtube to see what I mean!!! It's about turning waste into energy!!! Seriously, it's a game changer and could make a huge change in pollution AND the cost of utilities in the area! https://youtu.be/p6CF-umWLZg

    kt asked over 2 years ago

    Very interesting. Thank you for sharing.

Page last updated: 08 Nov 2024, 09:46 AM